Pre Plaster
PRE PLASTER Sample Report
It is important that the plaster is not installed before the pre plaster inspection, although often the builder has delivered the plaster already.
The following should be completed:
↳ All wall straightening is completed
↳ All outstanding frame inspection defects are completed
↳ Plumbing rough ins done
↳ Electrical rough ins done
↳ Ducted heating rough-ins done
Ideally the brickwork should be completed or at least a large amount so we can check the brick veneer wall cavity compliance. If the brickwork is not completed at this time and your builder is conducting a “reverse build